Just up the road from us in Dairy Flat, development is underway on a very unique project. On farmland between Postmans Road and Dairy Flat Highway, a surf park complex is being built that plans to warm its waves with spare heat from a neighbouring data centre. The surf park is newsworthy all on its own, especially for the Auckland region – but the data centre aspect makes it part of a larger, ongoing story.
You’ve probably noticed data centres in the news lately, with several large facilities in the works around New Zealand and debate over their challenges and benefits. One issue raised is the excess heat produced by servers, which most data centres vent into the air. The Dairy Flat plan would put that excess heat to use in the pool.
The project is led by Aventuur, an American surf park developer, in partnership with Auckland businessman Mark Francis, former Warriors chief executive Trevor McKewen and All Blacks great Sir John Kirwan. Kiwi actor Karl Urban and former All Black Marc Ellis have since invested. The surf park, data centre and an associated solar farm received resource consent in June 2024. Aventuur broke ground in February 2025. The park is due to open in 2028, and a proposed second stage would add nearly 500 homes around the water.
The surf park
So what will actually be there? The heart of it is a 2.2-hectare lagoon on It uses Wavegarden Cove technology from Spain, the same system behind existing surf parks in Melbourne and Bristol. It can produce waves to suit everyone from first-timers to experienced surfers.
The waves are made by machinery housed at the top of a pier that runs down the middle of the lagoon. Inside a row of modules, levers swing back and forth. Each swing pushes a wave out to one side of the pier, and the return swing sends another to the opposite side, so the lagoon offers left- and right-breaking waves at the same time.
Plans for the park include a surf academy, walking and cycling trails and restaurants as well as about 90 eco-cabins and a 50-room lodge. The developers expect the park to employ more than 120 people once it’s running, and more than 400 during construction.
How the site will work
Getting heat from the data centre into the surf lagoon will rely on a closed-loop system. Water will circulate through sealed pipes, picking up heat at the data centre and releasing it into the lagoon before flowing back for more. The developers say it is a world first.
The data centre will be run by TenPeaks Data Centres, which is jointly owned by Australian private equity firm Pacific Equity Partners and Spark New Zealand. The consented facility will be built in stages up to 40 megawatts, in a building about 16 metres high.
TenPeaks chief executive Michael Stribling says the cooling system does not rely on fresh water as its main method. Rainwater tanks are planned for the site, and the project is aiming for LEED Silver, an international green building rating. The on-site seven-hectare solar farm is expected to generate between 5 and 8 megawatts.
Questions and concerns
Reusing heat answers one of the questions people ask about data centres. On the subject of power consumption, the solar farm is the developer’s answer. However, at full size, the consented data centre would need more electricity than the solar farm can produce. So the question remains open.
The plans have also grown. The stage two application, now before a Fast Track expert panel, adds a “hyperscale AI data centre” to the project. Hyperscale facilities are the very large sites built for cloud computing and artificial intelligence. The newly proposed size has not been published.
During consenting, some neighbours raised concerns about noise, light and traffic. The plans include six 28-metre lighting columns around the lagoon. The site has no public wastewater or stormwater connections, so it will rely on an on-site wetland and a private wastewater network. TenPeaks says the data centre will meet Auckland Unitary Plan noise limits, with acoustic engineers overseeing the design.
Homes around the lagoon
The second stage is where the housing comes in: 486 homes, a village centre and live-work units across about 54 hectares. The land is zoned ‘Future Urban’, set aside by Auckland Council for growth. The project was referred to the Fast Track process in June 2025, and an expert panel was appointed in August. As of yet, no decision has been made.
Kirwan has compared the idea to golf course communities such as Millbrook near Queenstown and Te Arai north of Auckland. “It’s a new concept for New Zealanders, housing around a surf pool,” he told Stuff in June this year. “We want to be a positive thing in the community, bringing more houses and a different lifestyle opportunity for New Zealanders.”
A major new attraction nearby
The park looks set to open to a ready audience. Surfing NZ estimates about 330,000 New Zealanders surf, around 70,000 of them weekly. As Kirwan puts it, “There’s more surfboards than rugby balls in New Zealand.”
One-hour sessions are expected to cost about $100, with annual memberships also planned. Australian Glenn Hall, widely regarded as one of the great modern surf coaches, will oversee the academy, and Olympian Billy Stairmand is expected to take a senior role.
Aventuur’s director of surfing, Adrian Buchan, says consistent waves “flatten the learning curve”. “The ocean will always be our home,” he says, “but a wave pool is the perfect training ground.”
Up the road in Silverdale, Snowplanet has kept a 200-metre indoor ski slope at minus five degrees since 2005. Once the surf park opens, we’ll have indoor snow and heated surf within a short drive. Kirwan, for his part, plans to become a local. “I’ll sell my Mission Bay house and go up and live at the wave park!”.